Input export constraint at 750 kW. However, in output export limit is 375 kW.

cwilliams979
Tue, 07 Jun 2022 07:06:35 GMT

I am using the DER-VET software to size and simulate a solar battery energy storage site, with a 750 kW export constraint. However, setting the export constraint to 750 kW leads to only a max discharge of the BESS and solar to the grid of 375 kW in the time series results. Does anyone have any thoughts as why this is the case? I have tried changing multiple parameters with no success.

Andrew Etringer, EPRI
Mon, 20 Mar 2023 17:55:47 GMT

Thanks for this message. This issue was resolved in Version 1.2.3