Wholesale rate for excess generation at customer site?

lshaver
Wed, 19 Jan 2022 04:04:34 GMT

I am attempting to model a customer-sited BTM microgrid. Excess generation from the PV system will be sold back to the utility. Where do I enter the appropriate rate?

Andrew Etringer, EPRI
Mon, 31 Jan 2022 23:40:15 GMT

Hello and thanks for the message! There are two steps needed here: First turn on retail energy time shift (Project Overview -- Services page) Second, enter a retail energy tariff (The import rate is the same as the export rate)